PJM-AI2-123
35 MW generation in Fleming, KY · In queue since February 2023 · Proposed COD June 2025
35 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 4m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
PJM-AI2-123 is a proposed 35 MW solar generation project located in Fleming County, Kentucky. The project is listed in the PJM interconnection queue with an entry date of February 28, 2023, and a proposed commercial operation date of June 30, 2025. The interconnecting utility is EKPC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Goddard - Plumville 138 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Fleming
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Goddard - Plumville 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-123