PJM-AI2-124
23.3 MW generation in Fleming, KY · In queue since February 2023 · Proposed COD June 2025
23.3 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 4m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
PJM-AI2-124 is a proposed solar generation project with a total capacity of 23.3 MW, located in Fleming County, Kentucky. The project is being developed within the PJM Interconnection queue, with an entry date of February 28, 2023. The proposed commercial operation date is June 30, 2025. The Point of Interconnection (POI) is Goddard 138 kV.
The interconnection agreement (IA) for PJM-AI2-124 is currently in progress, with the specific study status unknown. The listed utility for the project is EKPC.
Generated from interconnection queue and public data sources
State
KY
County
Fleming
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Goddard 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Goddard Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-124