PJM-AI2-136
47.98 MW generation in Pulaski, IN · In queue since February 2023 · Proposed COD December 2022
47.98 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
PJM-AI2-136 is a proposed solar generation project with a total capacity of 47.98 MW. The project is located in Pulaski County, Indiana, and is interconnected within the PJM Interconnection region, with AEP as the utility. The queue entry date is February 28, 2023, with a proposed commercial operation date of December 31, 2022.
The interconnection status is listed as "In Progress (unknown study)". The point of interconnection (POI) is Olive - Reynolds 345 kV.
Generated from interconnection queue and public data sources
State
IN
County
Pulaski
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive - Reynolds 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-136