PJM-AI2-137
21.6 MW generation in Henry, VA · In queue since February 2023 · Proposed COD December 2022
21.6 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
PJM-AI2-137 is a proposed solar generation project with a total capacity of 21.6 MW, located in Henry County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 28, 2023. The proposed commercial operation date is December 31, 2022. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection (POI) is Stockton 138 kV.
The development project consists solely of solar generation, with a capacity of 21.6 MW.
Generated from interconnection queue and public data sources
State
VA
County
Henry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Stockton 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- STOCKTON69 KV LOADT2
- POI Substation
- Stockton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-137