PJM-AI2-139
54 MW generation in Union, OH · In queue since February 2023 · Proposed COD December 2023
54 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
10 months
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-25
PJM-AI2-139 is a proposed solar generation project located in Union County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 54 MW, consists entirely of solar photovoltaic technology. The interconnecting utility is AEP.
The project entered the PJM interconnection queue on February 28, 2023, with a proposed commercial operation date of December 25, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Marysville 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MARYSVI234.5 KV CADEN1SP
- POI Substation
- Marysville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-139