PJM-AI2-147
78 MW generation in Fountain, IN · In queue since February 2023 · Proposed COD December 2024
78 MW
Capacity
1
Components
Wind
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 10m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AI2-147 is a proposed wind generation project with a total capacity of 78 MW. The project is located in Fountain County, Indiana, within the PJM Interconnection region. The queue entry date is February 28, 2023, with a proposed commercial operation date of December 31, 2024. The interconnecting utility is AEP.
The project's interconnection status is listed as "In Progress (unknown study)". The point of interconnection is the Dequine - Eugene 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Fountain
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Dequine - Eugene 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-147