PJM-AI2-155
29.84 MW generation in Hardy, WV · In queue since March 2023 · Proposed COD December 2025
29.84 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI2-155 is a proposed wind generation project with a total capacity of 29.84 MW. The project is located in Hardy County, West Virginia, within the PJM Interconnection region and is being managed by utility APS. It entered the PJM queue on March 1, 2023, with a proposed commercial operation date of December 31, 2025.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Baker 138 kV II substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WV
County
Hardy
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Baker 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FOOTHILL18 KV UNIT 5
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-155