PJM-AI2-156
43.2 MW generation in Clark, OH · In queue since March 2023 · Proposed COD December 2026
43.2 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PJM-AI2-156 is a proposed solar generation project with a total capacity of 43.2 MW. The project is located in Clark County, Ohio, and is interconnected within the PJM Interconnection region, with ATSI as the utility. The queue entry date for the project is March 1, 2023, and the proposed commercial operation date is December 1, 2026.
The interconnection agreement for PJM-AI2-156 is currently listed as "In Progress (unknown study)". The point of interconnection is the East Springfield-London 138 kV III line.
Generated from interconnection queue and public data sources
State
OH
County
Clark
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
East Springfield-London 138 kV III
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-156