PJM-AI2-157
47.5 MW generation in Vinton, OH · In queue since March 2023 · Proposed COD December 2023
47.5 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
9 months
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-25
PJM-AI2-157 is a proposed solar generation project with a total capacity of 47.5 MW. The project is located in Vinton County, Ohio, and is interconnected within the PJM Interconnection region, with AEP as the utility. The project entered the PJM queue on March 1, 2023, with a proposed commercial operation date of December 25, 2023.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Elk 138 kV substation.
Generated from interconnection queue and public data sources
State
OH
County
Vinton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Elk 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ELKGARD2138 KV T1
- POI Substation
- Elk Garden Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.