PJM-AI2-165
72 MW generation in Clinton, OH · In queue since March 2023 · Proposed COD December 2023
72 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
9 months
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-25
PJM-AI2-165 is a proposed solar generation project with a total capacity of 72 MW, located in Clinton County, Ohio. The project is in the PJM interconnection queue, with an entry date of March 1, 2023, and a proposed commercial operation date of December 25, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project, which will interconnect at the Clinton - Stuart 345 kV point of interconnection, is being developed within the Dayton utility service area.
Generated from interconnection queue and public data sources
State
OH
County
Clinton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Clinton - Stuart 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.