PJM-AI2-166
78 MW generation in Logan, IL · In queue since March 2023 · Proposed COD December 2025
78 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-15
PJM-AI2-166 is a proposed wind generation project with a total capacity of 78 MW. The project is located in Logan County, Illinois, within the ComEd service area and the PJM Interconnection region. The project entered the PJM queue on March 1, 2023, with a proposed commercial operation date of December 15, 2025.
The interconnection agreement for PJM-AI2-166 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IL
County
Logan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Lanesville-Brokaw
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-166