PJM-AI2-168
32.4 MW generation in Adams, IN · In queue since February 2023 · Proposed COD December 2024
32.4 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 10m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AI2-168 is a proposed solar generation project with a total capacity of 32.4 MW, located in Adams County, Indiana. The project is interconnected within the PJM Interconnection queue as of February 28, 2023, with a proposed commercial operation date of December 31, 2024. The interconnecting utility is AEP, and the point of interconnection is the Magley 138 kV substation. The interconnection agreement status is currently "In Progress (unknown study)".
The development project consists solely of solar photovoltaic generation, with the 32.4 MW capacity attributed to solar resources.
Generated from interconnection queue and public data sources
State
IN
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Magley 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MAGLEY 138 KV ZODIACTP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.