PJM-AI2-170
39.12 MW generation in Delaware, IN · In queue since March 2023 · Proposed COD December 2022
39.12 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 2m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
The proposed project PJM-AI2-170 is a 39.12 MW solar generation project located in Delaware County, Indiana. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 1, 2023. The proposed commercial operation date is December 31, 2022.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection (POI) is the Delaware - Van Buren 138 kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Delaware - Van Buren 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-170