PJM-AI2-171
40 MW generation in Franklin, OH · In queue since February 2023 · Proposed COD December 2023
40 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
10 months
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-25
PJM-AI2-171 is a proposed solar generation project located in Franklin County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 40 MW, consists entirely of solar photovoltaic technology. The queue entry date is February 28, 2023, with a proposed commercial operation date of December 25, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the Cole Road 345 kV substation.
The development project is currently listed as "active" within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
OH
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Cole Road 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-171