PJM-AI2-174
36 MW generation in Cass, MI · In queue since February 2023 · Proposed COD December 2023
36 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
10 months
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-25
PJM-AI2-174 is a proposed 36 MW solar generation project located in Cass County, Michigan. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 28, 2023. The proposed commercial operation date is December 25, 2023. The interconnecting utility is AEP.
The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
MI
County
Cass
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Kenzie Creek - Colby 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-174