PJM-AI2-181
27.8 MW generation in Hardin, OH · In queue since February 2023 · Proposed COD June 2023
27.8 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
4 months
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-30
The proposed project PJM-AI2-181 is a 27.8 MW solar generation project located in Hardin County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 28, 2023. The proposed commercial operation date is June 30, 2023.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection (POI) is the Hardin Switch 345 kV substation.
Generated from interconnection queue and public data sources
State
OH
County
Hardin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hardin Switch 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-181