PJM-AI2-188
246.25 MW hybrid in Hardy, WV · In queue since March 2023 · Proposed COD March 2028
246.25 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-15
PJM-AI2-188 is a proposed solar and battery hybrid project with a total capacity of 246.25 MW. The development is located in Hardy County, West Virginia, and is interconnected within the PJM Interconnection region, with Allegheny Power Systems (APS) as the utility. The project consists of 246.25 MW of solar generation, and also includes battery storage.
The project entered the PJM interconnection queue on March 1, 2023, and has a proposed commercial operation date of March 15, 2028. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Mt. Storm - Meadow Brook 500 kV line.
Generated from interconnection queue and public data sources
State
WV
County
Hardy
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Mt. Storm - Meadow Brook 500 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-188