PJM-AI2-190
40.2 MW generation in Fayette, WV · In queue since March 2023 · Proposed COD March 2028
40.2 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-15
PJM-AI2-190 is a proposed solar generation project with a total capacity of 40.2 MW. The project is located in Fayette County, West Virginia, and is interconnected within the PJM Interconnection region, with AEP as the utility. The project entered the PJM queue on March 1, 2023, and has a proposed commercial operation date of March 15, 2028.
The interconnection agreement for PJM-AI2-190 is currently listed as "In Progress (unknown study)". The point of interconnection is the Carbondale 138 kV substation. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
State
WV
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Carbondale 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- East Carbondale Substation