PJM-AI2-194
15.8 MW generation in Hardin, OH · In queue since March 2023 · Proposed COD June 2025
15.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 3m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
PJM-AI2-194 is a proposed solar generation project located in Hardin County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 15.8 MW, consists entirely of solar photovoltaic technology. The interconnecting utility is AEP.
The project entered the PJM interconnection queue on March 2, 2023, with a proposed commercial operation date of June 30, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the South Kenton 138 kV substation.
Generated from interconnection queue and public data sources
State
OH
County
Hardin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
South Kenton 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MYSVL_EK138 KV LD_154
- POI Substation
- Kenton