PJM-AI2-197
108 MW generation in Pulaski, IN · In queue since March 2023 · Proposed COD December 2021
108 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
3y 2m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
PJM-AI2-197 is a proposed solar generation project with a total capacity of 108 MW, located in Pulaski County, Indiana. The project is in the PJM interconnection queue, having entered the queue on March 1, 2023. The proposed commercial operation date is December 31, 2021. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, which falls within the AEP utility territory, consists solely of solar photovoltaic generation. The point of interconnection is the Reynolds - Olive 345 kV line. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
IN
County
Pulaski
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Reynolds - Olive 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-197