PJM-AI2-203
1 MW generation in Salem, NJ · In queue since March 2023 · Proposed COD March 2023
1 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
<1 month
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-30
PJM-AI2-203 is a proposed solar generation project located in Salem County, New Jersey, with a total capacity of 1 MW. The project was entered into the PJM interconnection queue on March 2, 2023, with a proposed commercial operation date of March 30, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project, which is being developed within the Atlantic Electric Company (AEC) service area, consists of 1 MW of solar photovoltaic generation. The point of interconnection is at the Upper Pittsgrove 138 kV substation.
Generated from interconnection queue and public data sources
State
NJ
County
Salem
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Upper Pittsgrove 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- UPPERPIT138 KV PITSGVSP
- POI Substation
- Upper Pittsgrove Substation