PJM-AI2-204
1.55 MW generation in Gloucester, NJ · In queue since March 2023 · Proposed COD April 2023
1.55 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1 month
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-04-01
PJM-AI2-204 is a proposed solar generation project located in Gloucester County, New Jersey, within the PJM Interconnection region. The project, with a total capacity of 1.55 MW, consists entirely of solar photovoltaic generation. The interconnection request was submitted to PJM on March 2, 2023, with a proposed commercial operation date of April 1, 2023. The project's interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed point of interconnection is the Brokaw 345kV substation, and the interconnecting utility is PSEG. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
NJ
County
Gloucester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
Brokaw 345kV (CIR Increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-204