PJM-AI2-213
3.05 MW generation in Monmouth, NJ · In queue since March 2023 · Proposed COD March 2023
3.05 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
<1 month
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-29
PJM-AI2-213 is a proposed solar generation project with a total capacity of 3.05 MW. The project is located in Monmouth County, New Jersey, within the Jersey Central Power & Light (JCPL) service area and the PJM Interconnection region. The queue entry date was March 2, 2023, with a proposed commercial operation date of March 29, 2023.
The interconnection status for PJM-AI2-213 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Allenwood-Larrabee 2 34.5 kV line. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
NJ
County
Monmouth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Allenwood-Larrabee 2 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-213