PJM-AI2-219
45.2 MW generation in Erie, OH · In queue since March 2023 · Proposed COD November 2024
45.2 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 8m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
PJM-AI2-219 is a proposed solar generation project with a total capacity of 45.2 MW, located in Erie County, Ohio. The project is interconnected within the PJM Interconnection queue under queue ID PJM-AI2-219. The queue entry date is March 2, 2023, and the proposed commercial operation date is November 30, 2024. The interconnecting utility is ATSI.
The interconnection agreement (IA) status for the project is currently "In Progress (unknown study)". The point of interconnection (POI) is Groton 138 kV II.
Generated from interconnection queue and public data sources
State
OH
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Groton 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-219