PJM-AI2-222
47.8 MW generation in Lunenburg, VA · In queue since March 2023 · Proposed COD December 2024
47.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AI2-222 is a proposed solar generation project with a total capacity of 47.8 MW, located in Lunenburg County, Virginia. The project is in the PJM interconnection queue, having entered on March 2, 2023, under the utility Dominion. Its proposed commercial operation date is December 31, 2024.
The interconnection agreement (IA) for PJM-AI2-222 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Chase City-Lunenburg 115kV line. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
VA
County
Lunenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Chase City-Lunenburg 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-222