PJM-AI2-225
32 MW generation in Botetourt, VA · In queue since March 2023 · Proposed COD November 2025
32 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 8m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-03
PJM-AI2-225 is a proposed wind generation project located in Botetourt County, Virginia. The project, with a total capacity of 32 MW, is being developed within the Dominion service area. It entered the PJM interconnection queue on March 2, 2023, with a proposed commercial operation date of November 3, 2025.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Lexington-Low Moor 230kV line.
Generated from interconnection queue and public data sources
State
VA
County
Botetourt
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Lexington-Low Moor 230kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-225