PJM-AI2-226
120 MW storage in Licking, OH · In queue since March 2023 · Proposed COD August 2022
120 MW
Capacity
1
Components
Battery
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 2m
Schedule
45 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-08-22
PJM-AI2-226 is a proposed 120 MW battery storage project located in Licking County, Ohio. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of March 2, 2023. The proposed commercial operation date is August 22, 2022. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project, which is being developed within the AEP utility territory, consists solely of battery storage. It is interconnected at the Jug Street 138 kV point of interconnection. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Licking
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Jug Street 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- JUGSTRET138 KV T3
- POI Substation
- Jug Street Substation