PJM-AI2-236
22.6 MW generation in Campbell, VA · In queue since March 2023 · Proposed COD March 2023
22.6 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
<1 month
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-01
PJM-AI2-236 is a proposed solar generation project with a total capacity of 22.6 MW, located in Campbell County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 3, 2023. The proposed commercial operation date is March 1, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the Smith Mountain - Candler Mountain 138 kV line.
The project consists of 22.6 MW of solar photovoltaic generation. The developer is not specified in the queue data. The project's interconnection agreement is currently in progress, but the specific study being conducted is not identified.
Generated from interconnection queue and public data sources
State
VA
County
Campbell
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Smith Mountain - Candler Mountain 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-236