PJM-AI2-237
69.3 MW generation in Lancaster, VA · In queue since March 2023 · Proposed COD June 2024
69.3 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
PJM-AI2-237 is a proposed solar generation project located in Lancaster County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 69.3 MW, is being developed within Dominion's service territory. The project consists of 69.3 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue on March 3, 2023, with a proposed commercial operation date of June 1, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Garner DP-Lancaster 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Lancaster
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Garner DP-Lancaster 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-237