PJM-AI2-246
48 MW generation in Putnam, OH · In queue since March 2023 · Proposed COD December 2024
48 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-30
PJM-AI2-246 is a proposed solar generation project located in Putnam County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 48 MW, consists entirely of solar photovoltaic technology. The queue entry date for PJM-AI2-246 is March 2, 2023, with a proposed commercial operation date of December 30, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the East Leipsic - Richland 138 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Putnam
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
East Leipsic - Richland 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.