PJM-AI2-249
40 MW generation in Ross, OH · In queue since March 2023 · Proposed COD April 2023
40 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1 month
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-04-14
The proposed project PJM-AI2-249 is a 40 MW solar generation project located in Ross County, Ohio. The project is interconnected within the PJM Interconnection queue, with a queue entry date of March 2, 2023. The proposed commercial operation date is April 14, 2023. The interconnecting utility is AEP.
The project's interconnection status is listed as "In Progress (unknown study)". The point of interconnection is the Biers Run-Circleville 138 kV line. There is no identified developer or news coverage available for this proposed project.
Generated from interconnection queue and public data sources
State
OH
County
Ross
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Biers Run-Circleville 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.