PJM-AI2-250
10 MW generation in Fayette, OH · In queue since March 2023 · Proposed COD May 2024
10 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-31
PJM-AI2-250 is a proposed 10 MW solar generation project located in Fayette County, Ohio. The project is in the Dayton utility service area and is being managed within the PJM interconnection queue. The project entered the queue on March 2, 2023, with a proposed commercial operation date of May 31, 2024.
The interconnection agreement for PJM-AI2-250 is currently listed as "In Progress (unknown study)". The point of interconnection is the Greenfield 69 kV substation. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
State
OH
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Greenfield 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GREENFOE138 KV TR2
- POI Substation
- Greenfield Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-250