PJM-AI2-252
20 MW generation in Ross, OH · In queue since March 2023 · Proposed COD September 2024
20 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 6m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
PJM-AI2-252 is a proposed solar generation project located in Ross County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 20 MW, consists entirely of solar photovoltaic technology. The interconnecting utility is AEP.
The project entered the PJM interconnection queue on March 3, 2023, with a proposed commercial operation date of September 30, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Hillsboro-Clinton 138kV line.
Generated from interconnection queue and public data sources
State
OH
County
Ross
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hillsboro-Clinton 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-252