PJM-AI2-270
45 MW generation in Hardin, OH · In queue since March 2023 · Proposed COD February 2023
45 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-25
PJM-AI2-270 is a proposed solar generation project with a total capacity of 45 MW, located in Hardin County, Ohio. The project is being developed within the PJM Interconnection queue, with a queue entry date of March 3, 2023. The proposed commercial operation date is February 25, 2023. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the East Lima-Marysville 345kV line.
The project is interconnected with AEP. The project consists of 45 MW of solar generation. The project's status is listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Hardin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
East Lima-Marysville 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-270