PJM-AI2-272
32.6 MW generation in Beaufort, NC · In queue since March 2023 · Proposed COD February 2023
32.6 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-23
PJM-AI2-272 is a proposed solar generation project with a total capacity of 32.6 MW. The project is located in Beaufort County, North Carolina, within the Dominion service area and the PJM Interconnection region. The project developer is unknown.
The project entered the PJM interconnection queue on March 2, 2023, with a proposed commercial operation date of February 23, 2023. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Pantago-Five Points 115kV.
Generated from interconnection queue and public data sources
State
NC
County
Beaufort
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Pantago-Five Points 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.