PJM-AI2-279
43 MW storage in Richmond, VA · In queue since March 2023 · Proposed COD December 2026
43 MW
Capacity
1
Components
Battery
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-279 is a proposed 43 MW battery storage project located in Richmond County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 2, 2023. Dominion is the utility associated with the project.
The proposed commercial operation date for PJM-AI2-279 is December 31, 2026. Its interconnection agreement status is currently "In Progress (unknown study)". The point of interconnection is the Garner-Northern Neck 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Richmond
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Garner-Northern Neck 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-279