Project PJM-AI2-280 — Project Summary

Queue ID
PJM-AI2-280
Capacity
34 MW
Technology
Gas
Status
active
Location
Brunswick, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AI2-280

PJM-AI2-280BetaActiveGasPJMLBNL + Live

34 MW generation in Brunswick, VA · In queue since March 2023 · Proposed COD February 2023

34 MW

Capacity

1

Components

Gas

3y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

3y 2m

Schedule

39 months past proposed COD

In Study38%
Queue EntryMar 2, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-02-24

About

PJM-AI2-280 is a proposed 34 MW gas-fired generation project located in Brunswick County, Virginia. The project is in the PJM interconnection queue as of March 2, 2023, with a proposed commercial operation date of February 24, 2023. Dominion is listed as the utility.

The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Carson-Wake 500kV line.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Brunswick

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Carson-Wake 500kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AI2-280