PJM-AI2-290
9.1 MW generation in Wayne, OH · In queue since March 2023 · Proposed COD December 2026
9.1 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-290 is a proposed solar generation project with a total capacity of 9.1 MW, located in Wayne County, Ohio. The project is in the PJM interconnection queue, having entered on March 2, 2023, with a proposed commercial operation date of December 31, 2026. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, which will interconnect with ATSI at the Brookside-Cloverdale 138 kV II point of interconnection, consists solely of 9.1 MW of solar photovoltaic generation. The developer is currently unknown.
Generated from interconnection queue and public data sources
State
OH
County
Wayne
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Brookside-Cloverdale 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-290