PJM-AI2-292
4.9 MW generation in Adams, PA · In queue since March 2023 · Proposed COD December 2026
4.9 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-292 is a proposed solar generation project with a total capacity of 4.9 MW. The project is located in Adams County, Pennsylvania, within the PJM Interconnection region. The queue entry date is March 2, 2023, with a proposed commercial operation date of December 31, 2026.
The interconnection agreement (IA) status for PJM-AI2-292 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hunterstown-Texas Eastern Tap 115 kV III.
Generated from interconnection queue and public data sources
State
PA
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Hunterstown-Texas Eastern Tap 115 kV III
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-292