PJM-AI2-297
18.4 MW generation in Fulton, PA · In queue since March 2023 · Proposed COD January 2028
18.4 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
PJM-AI2-297 is a proposed solar generation project with a total capacity of 18.4 MW, located in Fulton County, Pennsylvania. The project is in the PJM interconnection queue, having entered on March 3, 2023, with a proposed commercial operation date of January 1, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is being managed within the APS service territory and connects to the McConnellsburg 138 kV point of interconnection.
Generated from interconnection queue and public data sources
State
PA
County
Fulton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
McConnellsburg 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MCCONNEL34.5 KV LETZB_SP
- POI Substation
- McConnellsburg Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-297