PJM-AI2-298
42 MW generation in Franklin, PA · In queue since March 2023 · Proposed COD January 2028
42 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
PJM-AI2-298 is a proposed solar generation project with a total capacity of 42 MW, located in Franklin County, Pennsylvania. The project is in the PJM interconnection queue as of March 3, 2023, with a proposed commercial operation date of January 1, 2028. The interconnecting utility is APS.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the McConnellsburg-Texas Eastern 138 kV line. There has been recent news coverage of this project.
Generated from interconnection queue and public data sources
State
PA
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
McConnellsburg-Texas Eastern 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-298