PJM-AI2-299
30.8 MW generation in Edgecombe, NC · In queue since March 2023 · Proposed COD December 2020
30.8 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Total Duration
3y 2m
Schedule
66 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-12-11
PJM-AI2-299 is a proposed solar generation project with a total capacity of 30.8 MW, located in Edgecombe County, North Carolina. The project is being developed within the Dominion service territory and interconnected to the PJM grid at the Benson-Dunbar 115 kV point of interconnection.
The project entered the PJM interconnection queue on March 3, 2023. Its proposed commercial operation date is December 11, 2020. The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
NC
County
Edgecombe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Benson-Dunbar 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.