PJM-AI2-302
26.9 MW generation in Harrison, KY · In queue since March 2023 · Proposed COD August 2024
26.9 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 5m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-30
PJM-AI2-302 is a proposed solar generation project located in Harrison County, Kentucky, with a total capacity of 26.9 MW. The project is being developed within the PJM Interconnection queue and was entered on March 3, 2023. The proposed commercial operation date is August 30, 2024. The interconnecting utility is EKPC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Jacksonville Tap - Renaker 138 kV line. Recent news coverage of the project may exist.
Generated from interconnection queue and public data sources
State
KY
County
Harrison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Jacksonville Tap - Renaker 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.