PJM-AI2-304
36.2 MW generation in Mason, WV · In queue since March 2023 · Proposed COD December 2026
36.2 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-304 is a proposed solar generation project with a total capacity of 36.2 MW. The project is located in Mason County, West Virginia, and is interconnected within the PJM Interconnection region, with American Electric Power (AEP) as the utility. The project entered the PJM queue on March 2, 2023, and has a proposed commercial operation date of December 31, 2026.
The interconnection agreement (IA) status for PJM-AI2-304 is currently "In Progress (unknown study)". The point of interconnection (POI) is at the Sporn South-Leon 138 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WV
County
Mason
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Sporn South-Leon 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.