PJM-AI2-313
17.1 MW generation in Meigs, OH · In queue since March 2023 · Proposed COD December 2023
17.1 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
9 months
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AI2-313 is a proposed solar generation project with a total capacity of 17.1 MW, located in Meigs County, Ohio. The project is in the PJM interconnection queue as of March 2, 2023, with a proposed commercial operation date of December 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, which interconnects to the Ravenswood-Hemlock 69kV point of interconnection, is being developed within the American Electric Power (AEP) service territory. The project is listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Meigs
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Ravenswood-Hemlock 69kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-313