PJM-AI2-316
19 MW generation in Woodford, IL · In queue since March 2023 · Proposed COD December 2024
19 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AI2-316 is a proposed wind generation project with a total capacity of 19 MW, located in Woodford County, Illinois. The project is in the PJM interconnection queue, having entered on March 2, 2023. Its proposed commercial operation date is December 31, 2024.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The interconnecting utility is ComEd, and the point of interconnection is Powerton 345 kV (CIR increase).
Generated from interconnection queue and public data sources
State
IL
County
Woodford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Powerton 345 kV (CIR increase)
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-316