PJM-AI2-353
16 MW generation in Allegany, MD · In queue since March 2023 · Proposed COD April 2024
16 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 1m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-01
PJM-AI2-353 is a proposed 16 MW wind generation project located in Allegany County, Maryland. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 3, 2023. The proposed commercial operation date is April 1, 2024.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is Carlos Jct. _x0013_ Ridgeley 138 kV, and the interconnecting utility is APS.
Generated from interconnection queue and public data sources
State
MD
County
Allegany
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Carlos Jct. _x0013_ Ridgeley 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-353