PJM-AI2-357
18.2 MW generation in Pulaski, IN · In queue since March 2023 · Proposed COD December 2025
18.2 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI2-357 is a proposed solar generation project located in Pulaski County, Indiana, within the PJM Interconnection region. The project, with a total capacity of 18.2 MW, consists entirely of solar photovoltaic technology. The queue entry date for interconnection is March 6, 2023, with a proposed commercial operation date of December 31, 2025. The interconnecting utility is AEP.
The project's interconnection status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IN
County
Pulaski
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive-Reynolds #2 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-357