PJM-AI2-360
45.9 MW generation in Mineral, WV · In queue since March 2023 · Proposed COD April 2023
45.9 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1 month
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-04-03
PJM-AI2-360 is a proposed wind generation project with a total capacity of 45.9 MW. The project is located in Mineral County, West Virginia, and is interconnected within the PJM Interconnection queue. The queue entry date is March 4, 2023, with a proposed commercial operation date of April 3, 2023. The Interconnection Agreement (IA) status is currently listed as "In Progress (unknown study)".
The project developer is unknown. The proposed point of interconnection (POI) is the Elk Garden - Parr Run 138 kV line, and the interconnecting utility is APS. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WV
County
Mineral
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Elk Garden - Parr Run 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Parr
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-360