PJM-AI2-365
32.06 MW generation in Preston, WV · In queue since March 2023 · Proposed COD September 2021
32.06 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
3y 2m
Schedule
56 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-09-30
The proposed project PJM-AI2-365 is a 32.06 MW solar generation project located in Preston County, West Virginia. The project is in the PJM interconnection queue, having entered on March 4, 2023. The proposed commercial operation date is September 30, 2021.
The interconnection agreement status is listed as "In Progress (unknown study)". The project's point of interconnection is the Lake Lynn-Hazelton 138 kV II line, and the interconnecting utility is APS.
Generated from interconnection queue and public data sources
State
WV
County
Preston
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Lake Lynn-Hazelton 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-365